Penalty Clauses and Rent Compensation in Flat-for-Land Construction Contracts

Author
Av. Cansu DENİZ
Published
Last reviewed

The construction contract in exchange for land shares, known in practice as the “flat-for-land construction contract” (kat karşılığı inşaat sözleşmesi), is a mixed contract under which the landowner undertakes to transfer ownership of specified land shares and the contractor, in return, undertakes to erect the building and deliver the agreed independent units. These contracts have become widespread with the renewal of existing buildings and urban transformation, and a large share of the disputes they give rise to stem from the failure to deliver the independent units on time.

A breach of the delivery obligation may deprive the landowner of the use of an independent unit and of rental income, and it may also make a penalty clause agreed in advance by the parties due. Not every monetary performance tied to a breach is a penalty clause, however: depending on the contract, a monthly payment may be a rent allowance, liquidated damages or a penalty cumulative with performance. Characterisation should therefore rest less on the name given to the payment than on the contract as a whole and on the real and common intention of the parties (art 19 of the Turkish Code of Obligations, TBK).

This article first explains the legal nature of the flat-for-land contract and the contractor’s default. It then examines the types of penalty clause, their validity and reduction, and the basis and calculation of rent compensation and its relationship with delivery. The focus is on the conditions under which a penalty and rent compensation may be claimed together. To that end, decisions of the 23rd Civil Chamber of the Court of Cassation (Yargıtay) from 2015 to 2018 and of its 6th Civil Chamber from 2025 to 2026 are assessed together, keeping the features specific to each case apart from the general legal principles.

A. Definition, elements and form

The flat-for-land contract is not a contract type separately regulated in the TBK; in legal writing and case law it is characterised as a mixed (dual-type) contract combining the elements of a contract for work and a promise to sell immovable property.1 The contractor’s obligation to erect the building is governed by the provisions on contracts for work in art 470 et seq TBK, and the landowner’s obligation to transfer land shares by the rules on the transfer of ownership of immovables. The reciprocity of these performances makes it a fully bilateral contract.

Because it includes the obligation to transfer land shares, the contract is subject to official form under art 706 of the Turkish Civil Code (TMK), art 237(1) TBK, art 26 of the Land Registry Law No 2644 and art 60 of the Notaries Law No 1512; official form is here a condition of validity. In practice, execution of the contract before a notary in the form of a notarial deed is accepted as sufficient.

As to the consequences of non-compliance with official form, the objection of abuse of rights based on the principle of good faith in art 2 TMK is important: where the performances have largely been rendered, invoking the defect of form may be treated as an abuse of rights. Even so, it cannot be said that the defect of form is cured automatically in every case, or that all supplementary protocols later concluded in simple written form are valid. In particular, penalty provisions added later that tilt the original balance of performances against the debtor should be subjected to a separate validity review (see II.E below).

B. Delivery obligation and default

The contractor’s obligation does not end with the physical completion of the building; the independent units must be delivered in conformity with the contract, the technical specifications, the project and the applicable legislation. If the contract leaves it to the contractor to obtain the occupancy permit (iskan; art 30 of the Zoning Law No 3194), the effect of that duty on the delivery obligation must be determined separately. That said, the mere absence of an occupancy permit does not justify the conclusion that a rent loss of the same extent continues in every case where the unit is actually used and yields an economic benefit.

Under art 117(1) TBK, the debtor of a due obligation falls into default upon the creditor’s notice. Where the date of performance has been fixed by the parties together, however, default occurs on the lapse of that date without notice (art 117(2) TBK). The Assembly of Civil Chambers of the Court of Cassation likewise holds that delay damages cannot be claimed where the contractor has not been duly put in default.2 In contracts where the delivery period depends on obtaining a building permit, vacating the land or the landowner taking a certain step, the date on which the obligation falls due and any extensions must be established on the basis of the concrete documents and conduct. The 6th Civil Chamber accordingly held, in a dispute where the delivery period was fixed at twenty-four months from the date of the building permit, that the delay penalty had to be calculated on that basis.3

In bilateral contracts, the granting of a reasonable period on the debtor’s default is governed by art 123 TBK, the cases in which no period is required by art 124 TBK, and the creditor’s options by art 125 TBK. As a rule, the creditor may claim specific performance together with damages for delay. If the creditor waives performance, positive damages are recoverable; if it withdraws from the contract, negative damages are. This distinction directly affects what becomes of a penalty tied to late delivery after the contract has ended (see V.A below).4

II. Penalty Clause (Cezai Şart, Ceza Koşulu)

A. Concept, accessory nature and function

The penalty clause, regulated in arts 179–182 TBK, is a performance that the debtor undertakes in advance to render to the creditor if it fails to perform at all, fails to perform properly, or fails to perform at the agreed time or place.5 Although the term cezai şart, established under the repealed Code of Obligations No 818, remains common in practice, the TBK adopted the term ceza koşulu; the two are used as synonyms in this article. The penalty clause is an accessory obligation dependent on the principal obligation; it serves both to sanction breach and to steer the debtor towards timely performance. Under art 180(1) TBK, the agreed penalty is payable even if the creditor has suffered no loss. This feature, which relieves the creditor of proving the existence and amount of loss, is the essential difference between a penalty clause and genuine delay damages.

B. Alternative penalty (penalty in lieu of performance)

Under art 179(1) TBK, where a penalty has been agreed for non-performance or improper performance of the contract, the creditor may, unless otherwise agreed, claim either performance or the penalty. Whether a penalty is alternative is determined by the wording of the contract and by the type of breach to which the penalty is tied. In its decision of 6 January 2026 (E 2025/176, K 2026/25), the 6th Civil Chamber upheld a regional court of appeal judgment holding that, since the landowners were pursuing their claim for the cost of remedying incomplete and defective work, the alternative penalty in the contract could not also be claimed.6

C. Penalty cumulative with performance and reservation

Under art 179(2) TBK, where the penalty has been agreed for failure to perform at the agreed time or place, the creditor may claim the penalty together with the principal obligation, unless it has expressly waived that right or accepted performance without reservation. Monthly or daily delay penalties for late delivery of independent units are mostly of this kind. Failure to reserve the right to the penalty on taking delivery leads, unless the contract validly provides otherwise, to the loss of the penalty claim.7

In its decision of 21 April 2025 (E 2024/2452, K 2025/1585), the 6th Civil Chamber assessed a contract providing that, if the delay exceeded three months, the landowners would receive, in addition to rent payments, a penalty of USD 1,000 per month. The Chamber held that this payment was a penalty cumulative with performance and that the reservation could be made before acceptance of performance by written notice, by an annotation on the delivery record or by any act indicating it; since there was no such reservation in the file, it found the acceptance of the penalty claim erroneous and reversed the regional court of appeal’s judgment.8

The decision shows clearly that the conditions for claiming genuine delay damages and for claiming a penalty cumulative with performance differ. Delivery records, notices, earlier proceedings concerning the dispute and correspondence between the parties should therefore be examined concretely.

D. Withdrawal penalty

Under art 179(3) TBK, the debtor retains the right to prove that it is entitled to terminate the contract by withdrawal or termination by paying the agreed penalty. Unlike the delay penalty, which sanctions default, a withdrawal penalty allows the debtor to exit the contract for a fixed price. The burden of proving that the agreed penalty is a withdrawal penalty lies with the debtor; absent such a stipulation, the penalty is as a rule interpreted as an ordinary penalty clause securing performance.

E. Validity, form and reduction of the penalty

Since the penalty clause depends on the principal obligation, no penalty can be claimed if the principal obligation is invalid for any reason or if performance becomes impossible for a reason for which the debtor is not responsible (art 182(2) TBK). According to the case law of the Court of Cassation, provisions later added in simple written form to a contract concluded in official form are valid only if they are supplementary ancillary terms that do not contradict the contract (art 13 TBK by analogy); arrangements imposing a new and more onerous obligation on one party are invalid unless official form is complied with. In its decision of 5 June 2018 (E 2015/8378, K 2018/3536), the 23rd Civil Chamber refused to give effect to a penalty provision that was absent from the main contract executed as a notarial deed, increased the contractor’s burden and had been introduced by a supplementary agreement in simple written form; it stated, however, that the claim for rent compensation based on the general provisions had to be examined separately.9

Under art 182(3) TBK, the judge reduces of its own motion a penalty it considers excessive. A debtor who is a merchant, however, cannot seek reduction on the ground that the penalty is excessive (art 22 of the Turkish Commercial Code, TTK); in the case law, this limit is softened under art 2 TMK in exceptional cases where the penalty would lead to the debtor’s economic ruin. In assessing reduction, the ratio of the penalty to the contract price, the length of the delay, the gravity of the breach, the economic situation of the parties and the creditor’s interest in performance should be considered together. A high penalty does not by itself require reduction.

III. Rent Compensation (Delay Damages)

Rent compensation is the indemnification of the loss the landowner suffers by being deprived, through late delivery, of the possibility of using or letting the independent unit. Its general basis is art 112 TBK together with the provisions on debtor’s default in art 117 et seq TBK, in particular art 118 TBK on delay damages. A separate rent compensation clause in the contract is therefore not required; if the conditions are met, delay damages may be claimed under the general provisions. Conversely, where the contract provides for a specific payment under the name of “rent”, interpretation must determine whether it compensates actual loss, is liquidated damages or is a penalty clause.

A rent allowance or compensation for deprivation of rights (hak mahrumiyeti bedeli) paid during construction because the existing building has been vacated may be an independent contractual obligation arising even without the contractor’s default. Rent compensation claimed for late delivery, by contrast, is as a rule tied to the fact that a unit not delivered on time cannot be used. The periods during which each of these two payment regimes applies under the contract are decisive for resolving the problem of double payment.

B. Conditions of the claim and proof

For a rent compensation claim, the court examines whether the delivery obligation was due, whether performance was delayed, the resulting economic loss and adequate causation. Under art 112 TBK, the contractor may escape liability by proving that no fault is attributable to it. In this context, the documents underlying defences such as the landowner’s failure to complete missing documents, failure to vacate the land, or refusal without good reason of a duly made tender of performance (creditor’s default, art 106 et seq TBK) should be assessed.

The fact that the landowner had not previously concluded a lease with a tenant does not mean that the loss of use has no economic value. The amount of loss may be determined by expert examination on the basis of comparable rents for the relevant periods. The calculation should, however, take into account the delivery date and the possibility of use separately for each independent unit.

Actual delivery is placing the independent unit at the landowner’s disposal. Legal delivery may, if the contract so provides, also include the fulfilment of conditions such as obtaining the occupancy permit. The moment the delay ends should not be determined on the assumption that these two facts automatically coincide in every case; the rent loss for a unit that has actually been let is not the same as that for a unit whose use is legally barred because there is no occupancy permit.

In the dispute underlying the 6th Civil Chamber’s decision of 20 May 2026 (E 2025/3027, K 2026/2197), the court of first instance characterised the claim based on a supplementary protocol as a penalty clause and dismissed it for lack of a reservation. The regional court of appeal held instead that the claim was for delay damages and, noting that delivery took place on 27 January 2015 instead of 30 September 2012, awarded TL 388,500 on the basis of the expert’s calculation; the Court of Cassation upheld that judgment, correcting the omission concerning the interest claim.10

The significance of the decision is that it shows that the reservation requirement in art 179(2) TBK, which is specific to a penalty cumulative with performance, cannot be applied to genuine delay damages on the ground that late delivery was accepted. The 23rd Civil Chamber had likewise held earlier that rent loss is compensation and that no reservation at delivery is needed to claim it.11 Nevertheless, the court must determine the nature of the claim by assessing all the provisions of the contract together.

D. Method of calculation

In calculating delay damages, the promised delivery date, any valid extensions and the date on which each unit was actually or legally delivered are established first; comparable rents are then determined period by period. For example, if three units with monthly comparable rents of TL 20,000, TL 25,000 and TL 30,000 are not delivered for six months during which those rents are assumed to remain unchanged, the rent loss is TL 450,000 (TL 75,000 × 6 months). In actual proceedings, changing market conditions and partial deliveries are also taken into account.

IV. Claiming the Penalty and Rent Compensation Together

A. The problem

Where a penalty has been agreed for the same delay in delivery and the landowner also suffers a rent loss, two distinct legal institutions come into play. This does not, however, justify adding the two amounts without limit in every case. It must therefore first be determined to which breach the penalty is tied, what the legal nature of the payment called “rent” is, and whether the parties expressly intended cumulative recovery.

B. Where cumulative recovery has not been expressly agreed

Under art 180(2) TBK, where the creditor’s loss exceeds the agreed penalty, the creditor may not claim the excess unless it proves the debtor’s fault. The provision governs the relationship between penalty and damages for the same breach and, unlike art 112 TBK, which places the burden of proving absence of fault on the debtor, it places that burden on the creditor as regards the excess loss. In its decision of 13 October 2016 (E 2015/936, K 2016/4530), the 23rd Civil Chamber stated that, unless the contract expressly provides that both claims may be pursued separately, only rent loss exceeding the penalty may be awarded alongside the penalty, and that if the rent loss is below the penalty the two amounts cannot be added together.12

For example, if the total penalty for the same period of delay is TL 400,000 and the rent loss established is TL 560,000, then, assuming that the contract contains no valid provision to the contrary and that the conditions for excess loss are met, the creditor may claim TL 160,000 of excess loss in addition to the TL 400,000 penalty. Had the loss been TL 300,000, the creditor could claim only the TL 400,000 penalty, irrespective of the amount of loss. This example is not an automatic application of court decisions; the type of penalty and the conditions for excess loss must be proved separately in each case.

C. Separate payment obligations expressly agreed

Within freedom of contract, the parties may agree on a penalty for the contractor’s late delivery and on compensation for the landowner’s rent loss independently of each other. This requires a clear intention to that effect in the contract; the mere use of the words “penalty” and “rent” in different clauses is not enough. In interpretation, art 19 TBK, the integrity of the contract, the provisions on standard terms (arts 20–25 TBK), reduction of the penalty and good faith should all be taken into account.

The 6th Civil Chamber’s decision of 3 March 2026 (E 2025/3099, K 2026/798) is a different example that makes this distinction visible. It concerned a claim for a double penalty tied to the incomplete or late payment of compensation for deprivation of rights agreed in the course of urban transformation; the Court reviewed the consistency between the reasoning and the operative part in calculating the contractual amounts and the set-off.13 The penalty at issue in that decision should be kept apart from a penalty tied directly to the late delivery of an independent unit.

It would therefore be wrong to present this decision as general authority that all delay penalties may be added to rent compensation. Its real significance lies in showing that the principal or ancillary obligation breached must be identified first.

D. Assessment in the light of recent decisions

Read together, the 2025 and 2026 decisions bring out the following distinctions: K 2025/1585 concerns acceptance of delivery without reservation in the case of a penalty cumulative with performance; K 2026/25 the relationship between an alternative penalty and claims relating to the principal performance; K 2026/2197 the consequences of distinguishing contractual delay damages from a penalty clause; and K 2026/798 a penalty tied to the obligation to pay compensation for deprivation of rights.

In the dispute underlying the 6th Civil Chamber’s affirming decision of 1 June 2026 (E 2025/3233, K 2026/2280), the parties disagreed on a daily delay penalty of TL 500 and on the nature of the contract; the contractor raised defences such as project changes, difficulties in obtaining the permit and the creditor’s default.14 While the decision illustrates that the cause of the delay and the parties’ performances must be assessed on the basis of the specific file, it cannot be said to lay down a new general rule, being a mere affirmance.

In our view, the correct method is to answer the following questions in order for each payment in dispute:

  1. To which breach is the payment tied?
  2. Is the payment a penalty clause, liquidated damages, a rent allowance or compensation for actual loss?
  3. Is the principal performance still being claimed?
  4. If delivery was accepted, was the right to the penalty reserved?
  5. Did the parties expressly and validly agree on separate recovery?

Only once these points are settled should the court move on to examine loss exceeding the penalty under art 180(2) TBK.

V. Termination, Limitation, Interest and Procedure

A. Ending the contract by withdrawal or termination

Whether the contract ends with retroactive effect (withdrawal) or prospective effect (termination) has different consequences for the claims. In the case law of the Court of Cassation, where construction has progressed substantially, withdrawal is held, by virtue of good faith, to produce the effects of prospective termination. On withdrawal, what becomes of a penalty tied to performance depends on the type of penalty and on any specific arrangement the parties have made for that event. On prospective termination, the settlement of rights that arose and fell due in the past must be assessed separately. In particular, it should not be assumed that a delay penalty cumulative with performance remains claimable automatically after withdrawal from the contract.

B. Limitation

For limitation purposes, the source of the claim, the type of payment, the date it fell due and whether any special provision applies must be considered. The five-year period for claims arising from contracts for work in art 147(6) TBK, and the exception for the contractor’s gross fault, should be assessed together with the general ten-year period in art 146 TBK and with regard to the mixed nature of the contract. For monthly penalty or rent payments, the due date of each claim should be examined separately; it should not be assumed that all claims become time-barred on the same day merely because there is a single contract.

C. Interest

Default in the obligation to deliver the unit and default in paying the monetary debt arising from that default are distinct. If the penalty or rent compensation was to be paid on a specific date, that date governs the start of interest; otherwise, the date of notice concerning the monetary debt or of the action does. Whether the dispute is a commercial matter and the type of interest sought (arts 1–2 of Law No 3095) should also be examined. In the decision K 2026/2197 mentioned above, the failure of the judgment to address the interest claim was corrected by the Court of Cassation.15

D. Jurisdiction, venue, procedural prerequisites and burden of proof

Under art 190 of the Code of Civil Procedure (HMK) and art 6 TMK, each party must prove the facts on which it bases its right. For a penalty clause, the validity of the clause and the breach triggering it must be proved; for delay damages, the loss, the period of delay and adequate causation. Records of evidence preservation, notarial notices, the building permit and occupancy permit, delivery records, comparable leases and expert reports are important in this respect.

As to subject-matter jurisdiction, the civil court of first instance is competent as a rule; if the dispute is a commercial case within the meaning of arts 4–5 TTK, the commercial court of first instance is competent, and other special rules may apply depending on the nature of the dispute. As to venue, the general rule in art 6 HMK and the court of the place of performance in art 10 HMK are the main options; if the claim is brought together with a claim in rem concerning the immovable, such as cancellation and re-registration of title, the exclusive venue rule in art 12 HMK must also be considered. As to mandatory mediation, if the dispute is a commercial case and concerns payment of a sum of money, applying to a mediator is a procedural prerequisite under art 5/A TTK. Art 18/B of Law No 6325, by contrast, covers disputes arising from leases, partition and dissolution of co-ownership, condominium and neighbour law, and so does not directly cover claims arising from a flat-for-land contract. In any event, the legislation in force on the date of application should be checked.

Conclusion

In flat-for-land contracts, a delay in delivery, though arising from a single fact, may give rise to distinct claims. The securing and sanctioning function of a penalty clause is distinct from the loss-compensating function of rent compensation. Labels used by the parties such as “rent”, “penalty” or “deprivation of rights” are therefore not decisive on their own; the real content of the contractual provision and the breach to which it is tied must be examined.

Depending on its type, a penalty clause may be alternative or cumulative with performance. In the case of a penalty cumulative with performance, acceptance of delivery without reservation extinguishes the penalty claim, but it has no such effect on genuine delay damages. Supplementary protocols made without official form that increase the debtor’s burden may also affect the validity of the claims. The Court of Cassation’s decisions of 2025–2026 confirm that these distinctions must be drawn on the facts of each case.

When a penalty and rent compensation are claimed together, it must be determined whether the parties expressly and validly agreed on separate recovery. Where there is no such agreement and the loss arises from the same breach, only loss exceeding the penalty may be claimed alongside it under art 180(2) TBK. Payment regimes tied to different breaches, on the other hand, should not be confused with one another.

In our view, disputes are best resolved by establishing first the breach and the delivery date, then the legal nature of the payments, and finally the amount of loss and the parties’ intention as to cumulative recovery. Contracts that regulate delivery and payment in detail and set out clearly how extensions and reservations are to be made will reduce problems of proof and help disputes to be resolved predictably.

Footnotes

  1. Hasan Erman, Arsa Payı Karşılığı İnşaat Sözleşmesi (3rd edn, Der 2010) 1–2; Cevdet Yavuz, Faruk Acar and Burak Özen, Türk Borçlar Hukuku Özel Hükümler (10th edn, Beta 2014) 1066–67; İsmail Atamulu, Kat Karşılığı İnşaat Sözleşmesinin Müteahhidin Temerrüdü Sebebiyle Sona Ermesi (Yetkin 2014) 25. ↩

  2. Yargıtay Hukuk Genel Kurulu (Court of Cassation, Assembly of Civil Chambers), E 2014/23-740, K 2016/283. ↩

  3. Yargıtay 6. Hukuk Dairesi (Court of Cassation, 6th Civil Chamber), E 2025/1791, K 2026/1160, 1 April 2026. ↩

  4. On the contractor’s default and its consequences in detail, see Atamulu (n 1); Mustafa Duhan Demir, “Kat Karşılığı İnşaat Sözleşmesinin Yüklenicinin Temerrüdü Sebebiyle Sona Ermesi” (Master’s thesis, İstanbul Medipol Üniversitesi 2016). ↩

  5. Köksal Kocaağa, Ceza Koşulu (Sözleşme Cezası) (2nd edn, Yetkin 2018) 25. ↩

  6. Yargıtay 6. Hukuk Dairesi, E 2025/176, K 2026/25, 6 January 2026. ↩

  7. On the nature, timing and proof of the reservation, see Burak Doğan, “İfaya Ekli Ceza Koşulunun Varlığı Halinde Çekince Beyanı” (2024) 28(2) Erzincan Binali Yıldırım Üniversitesi Hukuk Fakültesi Dergisi 775 https://doi.org/10.60002/ebyuhfd.1462664. ↩

  8. Yargıtay 6. Hukuk Dairesi, E 2024/2452, K 2025/1585, 21 April 2025. ↩

  9. Yargıtay 23. Hukuk Dairesi (Court of Cassation, 23rd Civil Chamber), E 2015/8378, K 2018/3536, 5 June 2018; to the same effect Yargıtay 23. Hukuk Dairesi, E 2015/6969, K 2015/8439, 24 December 2015. ↩

  10. Yargıtay 6. Hukuk Dairesi, E 2025/3027, K 2026/2197, 20 May 2026. ↩

  11. Yargıtay 23. Hukuk Dairesi, E 2015/8744, K 2018/4014, 5 July 2018. ↩

  12. Yargıtay 23. Hukuk Dairesi, E 2015/936, K 2016/4530, 13 October 2016; to the same effect the decision cited in n 11. ↩

  13. Yargıtay 6. Hukuk Dairesi, E 2025/3099, K 2026/798, 3 March 2026. ↩

  14. Yargıtay 6. Hukuk Dairesi, E 2025/3233, K 2026/2280, 1 June 2026. ↩

  15. The decision cited in n 10. ↩

This article is general information and not legal advice. Legislation and case law may have changed since the review date.